Why measure soiling before you build?
Because the soiling number goes into the energy yield model, the design and the O&M budget before anyone has measured it. IEA PVPS puts it plainly: the impact of soiling on a proposed plant’s energy yield and O&M costs can be understood in advance by measuring soiling on the site before installation, which needs a soiling sensor running for at least a year (IEA PVPS 2022, §4.1).
That year of data settles three things that are otherwise assumed:
- the soiling loss in the energy yield model;
- design choices such as tilt, tracker stow, row layout and the module itself;
- the cleaning method, interval, water plan and budget in the O&M contract.
Many of those models are being written now: South Africa’s IRP 2025 plans 10,313 MW of new solar PV for 2026–2030 (DMRE).
What does the soiling assumption do to the yield model?
In an energy yield model, soiling is an assumed loss: usually one annual percentage, or one value per month. Whatever you assume comes straight off the modelled energy. On an illustrative 10 MWp fixed-tilt plant near Upington, producing about 19.9 GWh a year (Global Solar Atlas), each 1% of soiling is about 199 MWh a year. That is roughly R0.87 million a year at the REIPPPP bid window 1 tariff of R4.39/kWh, R0.22 million at bid window 4 (R1.10/kWh) and R0.10 million at bid window 6 (R0.49/kWh). Run your own case in the soiling loss calculator.
Three things make a borrowed number risky in Southern Africa:
- Little local data. We found no peer-reviewed PV soiling rates for Upington, Kathu, Prieska, Kimberley, Namibia or Botswana. The South African measurements that do exist range widely; they are in soiling losses in South Africa.
- Models struggle at low losses. When two soiling models were compared across 20 locations, they correlated poorly where average losses were below 5%, and the same model gave different answers with different particulate-matter datasets (IEA PVPS 2022, citing Pelland et al.).
- Neighbours soil differently. Soiling is not uniform across a site, depending on where the dust comes from and the prevailing wind. See soiling ratio, rate and loss explained.
What a year of data changes in the design
| Design decision | What the soiling data tells you | Evidence |
|---|---|---|
| Tilt | How much a steeper tilt would cut soiling | Soiling losses typically fall as tilt rises (IEA PVPS 2022) |
| Tracker night stow | Whether stowing modules face-down at night is worth specifying | At IIT Bombay, a module flipped face-down at night soiled at 0.14% a day, against 0.45% for a fixed module (IEA PVPS 2022, §6.1.3) |
| Bifacial or monofacial | How much of the rear-side gain survives soiling | At the same site, latitude-tilted bifacial modules soiled at 0.32% a day and monofacial ones at 0.45%, because the rear side barely soils (IEA PVPS 2022) |
| Row layout | Which blocks sit downwind of roads, pans, quarries or cement works | IEA PVPS advises designing with wind direction, rain, humidity and dew in mind, and lining dirt roads with vegetation to deflect dust (§6.1.1) |
| Module choice | Whether the site’s cleaning water suits the module maker’s limits | Maker limits are in water quality for solar panel cleaning |
| Coating budget | Whether an anti-soiling coating is likely to pay | A hydrophobic coating increased soiling in a Northern Cape trial (du Plessis et al. 2020) |
The Mumbai results come from a warm, humid site, so treat them as the direction of the effect; your own site sets the size.
Water deserves a line of its own. If the only affordable source is hard borehole water, the module you choose decides whether crews can wash with it as it is, need to soften it or need reverse osmosis. Test the source before the module is specified. The maker-by-maker limits are in water quality for solar panel cleaning.
What it changes in the O&M budget
- Number of washes. The right interval depends on your tariff, soiling rate and what a clean costs, and it changes with the season. The calculator works it out for your plant. A measured soiling rate turns that into a budget line.
- Water. A wet wash uses about 1–3 L/m² (NREL 2018; Naicker 2018), or roughly 50–150 m³ for one full wash of a 10 MWp plant. South Africa averages about 490 mm of rain a year (WWF-SA), and the national water plan projects a shortfall equal to 17% of supply by 2030 (DWS). Multiply the washes by the volume before you sign for the water.
- Method. Loose dust may not need water at all: dry cleaning versus distilled water at Kalkbult is in soiling losses in South Africa. Dust that dew cements onto the glass needs a wet clean with the right chemistry (IEA PVPS 2022). What you measure decides between a dry robot, a tractor brush with water and a crew with removal agents. Cleaning robots cost €2.4–8.2/m² in capital and remove more than 95% of soiling (Ilse et al. 2019).
- Monitoring. Class A monitoring and how many sensors a site needs are in soiling ratio, rate and loss explained. A pre-construction station shows where the operational sensors should go.
What does a pre-construction soiling study involve?
A useful study has five parts:
- A site walk to map the dust sources upwind of the array: roads, pans, quarries, cement works, farmland and bird roosts.
- A soiling station at the planned tilt, and on a tracker if the plant will track: a reference device cleaned on schedule beside one left to soil, logging daily, with rain, wind and humidity measured alongside.
- A full year, so the data covers the dry and the wet season, with soiling rates fitted over a dry spell long enough to trust; see soiling ratio, rate and loss explained. Large sites need more than one station.
- Dust and water samples. Lab analysis shows what the dust is made of and whether it is likely to cement; in the Green Energy Park trial in Morocco, the dust was rich in calcium oxide, silica and phosphorus pentoxide (Elamim et al. 2023). The water is tested against the short-listed module makers’ limits.
- Outputs your team can use: a month-by-month soiling loss for the yield model, design notes, a cleaning method, interval and water plan, and the inputs for the O&M budget.
See our new-plant soiling study for how we set one up, and soiling measurement for the stations and sensors we use on operating plants.
CSP plants have even more at stake. Why CSP soiling costs more than PV soiling is in CSP. Test mirrors near a ferromanganese smelter at Emalahleni lost an average of 32.6% of their reflectance per 14 dry-season days (Swart et al. 2023). For a new mirror field, measure reflectance loss on sample mirrors on the site itself. See CSP mirror reflectivity.
If construction is close. A full year is what IEA PVPS describes, but a shorter campaign still tells you more than a default. The first dry spell long enough to fit a soiling rate gives a figure for the season that matters most; see soiling ratio, rate and loss explained. The station can stay on through construction into operation. For very large plants already running, a full plant study applies the same measurement to cleaning economics.
About this post
Sources
- IEA PVPS Task 13, Soiling Losses – Impact on the Performance of PV Plants (T13-21:2022), §4.1, §4.1.5, §6.1.1 and §6.1.3
- IEA PVPS Tasks 13 and 16, soiling fact sheet (September 2025)
- IEC 61724-1:2021, Photovoltaic system performance: Monitoring
Show all 21 sourcesShow fewer
- DMRE, Integrated Resource Plan 2025 (user-friendly version), Table 1
- Global Solar Atlas, Upington site data
- IPP Office, REIPPPP tariffs by bid window (September 2020)
- Government of South Africa, media statement on REIPPPP bid-window tariffs (8 December 2022)
- du Plessis, MEng thesis on soiling at Kalkbult, Stellenbosch University (2017)
- du Plessis et al., IET Renewable Power Generation 14(15) (2020)
- Ilse et al., Techno-economic assessment of soiling losses and mitigation strategies, Joule 3:2303–2321 (2019)
- NREL (now the National Laboratory of the Rockies), Best Practices for O&M of PV and Energy Storage Systems, 3rd ed. (2018)
- Naicker, Investigating the O&M strategy of solar PV plants in South Africa, MBA mini-dissertation, North-West University (2018), hosted by SAPVIA
- WWF-SA, Water: Facts and Futures (2016)
- Department of Water and Sanitation, National Water and Sanitation Master Plan, draft (2018)
- Trina Solar, User Manual, Vertex Series, UM-M-0002 Ver. L (August 2024)
- Aiko, PV Modules Installation Manual 2503V15 (March 2025)
- Huasun, HJT Module Installation Manual (2024), distributor-hosted copy (Solar Link Australia)
- Znshine, Installation Manual for Single Glass PV Modules, 026G-IEC (2024)
- First Solar, Module Cleaning Guidelines, PD-5-804 Rev 3.4 (2017)
- Elamim et al., Performance analysis of innovative cleaning and soiling mitigation solutions in the semi-arid climate of Benguerir Morocco, Heliyon 9, e16163 (2023)
- Swart et al., Journal of the Southern African Institute of Mining and Metallurgy 123(6) (2023)